The global electrical infrastructure sector is grappling with an unprecedented supply chain crisis: a severe, structural global transformer shortage. What was historically a straightforward electrical equipment procurement cycle has transformed into a high-stakes bottleneck. Across North America, Europe, the Middle East, and Latin America, delivery timelines for power transformers and liquid-filled distribution transformers have expanded drastically. Lead times that averaged 6 to 12 months before 2020 have skyrocketed, frequently stretching between 24 to 48 months (128 to 160 weeks) for larger units. For EPC contractors, industrial plant developers, renewable energy engineers, and utility companies, this supply delay represents a critical risk to commercial operation dates (COD). Below, we analyze the […]